On the home stretch – it’s getting cozy!
- Kreuzheim
- May 16
- 1 min read
Progress is moving at full speed – there's bustling activity on the construction site, and work is underway in every corner!
Facade work: successfully completed
The townhouses are also finished, and the scaffolding will be dismantled next week.
Tiling
Tiling work in the apartments is nearly complete – only one bathroom on the 5th floor still remains to be done.
Painting
All apartments have been fully wallpapered and have received their first coat of paint. The next steps in the interior finishing will include a final second coat by our painters.
Staircase
The tiling work in the stairwell has begun!
Utilities and Infrastructure
A significant milestone has been reached: the first phase of the utility infrastructure has been completed. The connections between the old front building and our new development have been successfully installed.
Roofing
Nearly all preparatory work has been completed this week, allowing us to move into the final phase. In the next two to three weeks, the roofs will be greened and the balconies and rooftop terraces will be fitted with flooring.
Outlook
The following work is still to be done before final completion:
Installation of all interior doors
Bathroom facilities
Final assembly by the electrician
Installing skirting boards in the living areas
Commissioning of building technology
Outdoor area
Work on the outdoor area will also begin in early June, carried out by our landscaping team.
We continue to work at full speed and will keep you regularly updated on further progress!